Thursday, September 28, 2006

First Floor Lighting


More electrical rough-in's. Here are the can lighting in the living room. Those on the righthand side will be wall washers for the fireplace wall. Posted by Picasa

Holddowns


Holddowns are getting placed..we're hoping for our framing inspection to happen on Monday. Posted by Picasa

Wednesday, September 27, 2006

Crawlspace Framing


The wall dividing the basement and crawlspace has been framed out. That wider opening will be our access to the crawlsapce. Judging from the limited access to the furnace, I'm guessing that I will get to be the one crawling in there to change filters..unless I can train Lola to do it.. Posted by Picasa

More Trench


Nice trench... Posted by Picasa

Basement Dewatering System


Looks like Dugan's starting to dig the perimeter trenches for the basement dewatering system. We used to get some water coming in the basement during the heavier rains and it seems like it was coming up from under the slab through little pin holes in the concrete, probably through hydrostatic pressure. We figured that it'd be a good idea to take care of that issue while we're doing the rest of the house. Posted by Picasa

Master Shower


They moved our shower unit into the bedroom and looks like they had to cut the door opening to get it through! Posted by Picasa

Starting Electrical


They are starting to put in the electrical boxes, starting with the second floor. We've been trying to finalize our reflected ceiling plans and picking out all of the fixtures. Let's just say there's a lot about can lighting that we never knew about.

Saturday, September 23, 2006

Basement Rec Room Framing


It's hard to see but we furred out the columns into these fat columns to cover them up and to match each other. The recessed areas will be great for bookshelves in the future. Posted by Picasa

Basement Laundry Room Framing


Basement framing is almost finished. This wasn't originally part of the plan but since it was easy to tear out the existing walls, we figured it'd be best to reconfigure the basement now, rather than later. This is a view of our future laundry room. Posted by Picasa

Existing Bathroom Floor


Our gamble paid off - there was a big trapezoidal vanity against that wall and we were pretty sure that this nice original hex tile would run all the way underneath it and sure enough, it does. We'll be replacing that vanity with a pedestal sink. The tiny triangular sink that was in the trapezoidal vanity is now laying on the back lawn and the old toilet sitting in front of the house...in case anyone is interested!

Drag Strut


We had to rip out the ceiling of the existing bathroom to get that drag strut (horizontal metal bar) across and through the deck beams. I was going to explain its purpose but then I forgot. Mike, feel free to chime in...

Interior Strapping


View from the interior of the LSTA straps Posted by Picasa

That's a LOT of Strapping



The second floor and first floor come together here at the stair window and the wall here essentially acts like a hinge so we had to strap and nail the heck out of it. We had to repeat the strapping on the inside of the wall as well.

Saturday, September 16, 2006

Happy Birthday Lola!


Being a two-year old isn't too hard - all you need is a pair of sassy sunglasses and stickers on your shirt. Of course we made a visit to the house today for her to jump off the wood piles in celebration. Posted by Picasa

Roof Complete!


Our roofing has been installed. Posted by Picasa

Our Fat Shower


Here's our big shower unit for our master bathroom. Posted by Picasa

Second Floor Ductwork


I know, so exciting. Here's an example of the ceiling ductwork for the bedrooms. Posted by Picasa

Fireplace Installed


There's our double-sided fireplace, sitting in place.

HVAC closet


They framed out this closet and stuck a bunch of hvac ductwork in it. We'll have floor registers on the first floor and ceiling registers on the upper level (apparently for efficiency) Posted by Picasa

Octopus Arms


It's really a thing of beauty. Posted by Picasa

Modern Day Octopus



We were going for that Old World Charm so we had them install a modern day Octopus furnace. Can you tell which photo is ours???
Ok, just kidding but I'd still like to ask Dugan about why those ducts seem so huge. The furnace is a Trane, high efficiency (>90%FLUE) unit and it's nice that they were able to tuck it into the crawlspace.

Monday, September 11, 2006

Mechanical Stuff


The see-thru fireplace has arrived...it'll go in that central wall in the living/dining room. Dugan has roughed in the gas lines for both the fireplace and the range. The sheet metal guys were here today doing some HVAC work. Posted by Picasa

Plumbing has started


Dugan has started putting in the vent pipes for all the plumbing in the house. Posted by Picasa

Who loves you?

You know your construction project has consumed your life when your contractor makes it into your child's nightly "Who loves you" list. I ask Lola every night, "Who loves you?" and she usually says, "mama, daddy, ama (grandma), etc." and the other night, after naming all the usuals, she also said, "doo-goon" (Dugan)

Saturday, September 09, 2006

What's Next

Well, it did rain last night, our first downpour for the entire summer, which means that the roofing felt went on not a day too soon. They will be starting to rough in the plumbing next week and electrical in a couple weeks. The inspector will be coming out in the next couple weeks too, to sign off (hopefully) on framing/holddowns.

Friday, September 08, 2006

Not for the squeamish


So one of the roofers shot himself in the foot today with his nail gun while getting on that steep corner of the roof. He was setting his nail gun down when it went off and the nail shot into his BONE about 3/8" of the way, through the cartilege and deep enough so that he couldn't pull it out with pliers. Damn...
Dugan insisted that they finish the job (cover the roof with felt at a minimum) because it's supposed to rain tomorrow, so he had the poor guy sit in his truck and drink water to keep himself hydrated (since he was bleeding) and wait for his partner to feverishly finish the work so that he could drive him to the hospital.
I don't know about you, but I don't complain about my job anymore.

Roofing


As Lola would say, Niiiiiiice. They put up the roofing felt today so our roof is officially protected from the rain. They even got some of the roofing up as well, in the back corner of the house. (see next story) Posted by Picasa

Deck Framing


Another view of the lovely deck. Posted by Picasa

Master Bedroom Deck Framing


Deck framing for the deck off the master bedroom went up. Posted by Picasa

Tuesday, September 05, 2006

Stair window


Looks like they finally cut the rim joist and finished framing out the window at the staircase. The idea was to help light the stairwell since it's not completely open and hopefully the light will spill into the dining room as well as the hallway upstairs.

Stairs















Our stairs are in! They will be eventually carpeted down to the last landing and then the carpet will turn into a runner down the rest of the stairs. The bottom 4 treads will be either bamboo or oak, with the last tread wrapping around into an "L" shape ( you can see it framed out in the photo)