Thursday, December 21, 2006

Merry Christmas Everyone!!


I probably won't be posting for a week or so. Have a Merry Christmas everyone!




Appliances have arrived!


Just came today - the range, hood, dishwasher and microwave. We're reusing our refrigerator - it's going to be tricky getting it back in the house though - that sucker was HEAVY!

Second Floor Paint


Both floor are now painted.

First Floor Paint


We had them paint the whole house in one color and will do any accent walls ourselves in the future. Color is a Benjamin Moore paint called White Chocolate.

Basement Drywall


Basement walls are drywalled, taped and mudded.


Hard to see but this is our future "family/media room"

Thursday, December 14, 2006

Laundry Room


The concrete has been poured for the laundry room floor. Dugan used concrete instead of gypcrete because we'll be leaving the laundry room floor bare (sealed concrete). We'll be doing gypcrete in the rest of the basement since we'll put some sort of finish on top of it, probably carpet.

Mud and Tape


This is the wall between the crawlspace and basement. The black material at the bottom is a waterproofing membrane.

Living Room

Master Bedroom

Tuesday, December 05, 2006

Drywall Complete!


Here's Lola in her future room...

Or maybe it'll be this one?

View from the front - you can see the drywalled ceiling and walls inside.
Dugan is currently working the concrete in the basement and has poured the sidewalk concrete (just a minimal area to patch where the porch used to be)

More Drywall


The spaces feel so different with all of the drywall installed!
Here are Derek and Lola doing a walk-through on the first floor.


Here's a view of the dining/living room, standing from the stairs.

Sunday, December 03, 2006

Insulation Complete and Drywall in Process

They finished the insulation on Thursday and have been installing drywall all weekend. I'm having problems uploading photos so I will try again tomorrow!